Northern Manitoba Mill Expands Throughput 2.5x and Delays a New Mill Build

The Situation

A mining company in Northern Manitoba needed more mill capacity to process ore from a new mine in the Snow Lake area. Building a new mill was a major capital cost, so the company chose to expand its existing mill first. The upgrade would restart zinc extraction and increase throughput for both zinc and copper.

Celco, a Tavoron company, designed and supplied the electrical and control systems for the expansion. Mill capacity grew from 1,500 to 4,000 tonnes per day, and the customer can now delay building a new mill by about 4 years.

The Challenge

The expansion had to buy the customer time before a new mill would be needed. Some new, larger equipment was purchased, including cyclones and filters, but much of the existing mill equipment would be repurposed in the expanded process.

The project had to:

The Solution

The Celco team started by evaluating the electrical and control systems on the existing equipment to decide what could be reused or upgraded. Their experience on previous mill and mining projects helped them quickly assess the older equipment and recommend migration approaches to meet current standards.

Key system elements included:

Instead of running hundreds of feet of multiconductor cable, Celco designed an Ethernet remote I/O system throughout the mill. That cut both installation time and wiring costs. Because Celco designed and supplied the electrical and control hardware, the team could choose the most cost-effective approach for the customer at every step.

The Results

Looking Ahead

By getting more out of its existing mill, the customer turned a major capital project into a planned future investment. The upgraded controls, safety systems, and Ethernet network also give the mill a modern foundation for continued operation.